Grand Bahama’s Rand Memorial Hospital is finally approaching the completion of its long-awaited morgue renovation project after a significant delay caused by a manufacturer’s error. Health Minister Dr. Michael Darville confirmed the timeline during the annual Governor General’s visit to the facility on Friday.
The $1.6 million modernization project, which began over two years ago in June 2022, faced substantial setbacks when equipment provided by the manufacturer proved incompatible with the renovated space. “Our morgue facility was delayed tremendously because of an error from the manufacturer who sent us a system that could not fit the renovated space,” Dr. Darville explained. “After extensive negotiations, the problem has been corrected and we are back on track.”
The urgency of the situation was highlighted earlier this month when a temporary refrigerated trailer used for body storage collapsed and required replacement, raising public concerns about the facility’s conditions.
Dr. Darville acknowledged broader challenges with capital works at the hospital, stating: “There have been many setbacks, frustrations, and challenges, but I want to let the people of Grand Bahama know that even though they are not completed, we are moving rapidly to complete this work before our term in office is over.”
Beyond the morgue project, several other healthcare infrastructure initiatives are progressing. Renovations to the hospital’s modular units are ongoing with completion expected in first quarter 2026, which Dr. Darville said would “restore the dignity of the final chapter” for affected services.
Additionally, a contract has been awarded for the renovation of Davies House to expand oncology and mammogram services, allowing patients to receive specialized care locally. The Freeport Health Centre construction remains on schedule, with phase one targeting completion in second quarter 2026. Phase two, featuring inpatient surgical suites, urgent care facilities, and replacement beds for Rand Memorial Hospital, will proceed following a tender process in early 2026.