PURE deputy director fired

Hayden Phillip, former second-in-command of Trinidad and Tobago’s Programme for Upgrading Roads Efficiency (PURE) under the Ministry of Works and Infrastructure (MOWI), has been summarily dismissed following a sweeping series of internal and cross-agency audits that uncovered systemic governance failures, unethical procurement practices, and potential misuse of hundreds of millions of dollars in public infrastructure funds. The September 25, 2026 termination order, delivered via a 12-page official letter signed by MOWI Permanent Secretary Ian Ramdahin, accuses Phillip of gross misconduct, public office malfeasance, and fundamental breaches of his employment contract, with immediate effect barring him from accessing all ministry premises, databases, financial systems, and official communication channels, and requiring him to surrender all state-owned PURE and MOWI property in his possession.

Established in 2002 as a short-to-medium term intervention to address Trinidad’s rapidly deteriorating national road network, PURE gradually expanded into a full-scale, high-budget infrastructure management unit overseeing road rehabilitation, highway expansion, bridge construction, landslip remediation, and other critical public works across the country. The termination letter notes that Phillip’s appointment as deputy programme director never went through a formal competitive recruitment process, and was improperly influenced by a close relative employed within the MOWI.

The investigation that led to Phillip’s ouster traces back to a preliminary 2025 internal enquiry, which triggered follow-up probes by MOWI’s Internal Audit Department and the Ministry of Finance’s Central Audit Division. The most severe allegations against Phillip center on unreported conflicts of interest and improper personal benefits from contractors awarded lucrative state PURE contracts. Official documents name three companies registered under Phillip and two of his immediate relatives: Roads and Buildings Services Ltd, Lot #19 Villas Ltd, and Omnia TT Ltd. Investigators allege the $3.1 million Millennium Lakes condominium linked to Lot #19 Villas Ltd was directly transferred to Phillip by the directors of a major PURE contractor that had secured multiple multimillion-dollar public works deals. The MOWI further claims Roads and Buildings Services Ltd was used to funnel materials, labour, and business opportunities to affiliated firms in exchange for state contract awards, a violation of core public sector internal control rules designed to prevent corruption.

Audits also exposed a near-total absence of basic operational guardrails across the entire PURE unit, despite its stewardship of hundreds of millions of dollars in annual public funding. Investigators confirmed PURE had no formal written standard operating procedures for core functions including project management, quality assurance, risk assessment, budget tracking, contract administration, dispute resolution, or progress reporting. The unit maintained almost no formal written records of its activities and submitted no structured progress updates to MOWI headquarters, creating massive blind spots that rendered routine oversight and independent audits nearly impossible. No mandatory financial risk assessments were ever conducted on major high-value projects, and the unit had no formal policies in place to prevent fraud, collusion, conflicts of interest, or other unethical behaviour. This lack of basic governance also created dangerous information silos between PURE and MOWI leadership, leading to redundant project planning and widespread inefficient allocation of scarce state infrastructure resources.

A large portion of the investigation focused specifically on the high-profile Sir Solomon Hochoy Highway expansion project, which involved adding new travel lanes along the Chaguanas to Chase Village stretch of the national roadway. Auditors documented pervasive project mismanagement including delayed decision-making, poor inter-departmental coordination, flawed initial design work, and lax contract supervision. Most notably, the unit failed to escalate a $38 million extension of time claim submitted by primary contractor Seereeram Brothers Ltd to MOWI’s legal team in a timely manner, a misstep that could have been mitigated with proper oversight to save the ministry significant time and public funds. PURE leadership also repeatedly failed to flag early warning signs of contractual disputes to senior MOWI officials, allowing minor issues to escalate into costly, unresolvable conflicts.

Probes also identified major structural flaws in the joint procurement framework operated by PURE and the National Infrastructure Development Company Ltd (Nipdec). Bids for high-value public contracts were evaluated exclusively by internal PURE and Nipdec staff, with no independent representation from MOWI leadership, legal counsel, certified procurement specialists, or external industry experts. This closed, insular review ecosystem eliminated almost all transparency safeguards, creating a high-risk environment vulnerable to both actual and perceived bias, favouritism, and conflict of interest. Investigators also found no documented records of required reviews from Nipdec’s mandatory Project Definition and Advisory Committee (PDAC), the body formally tasked with signing off on all major procurement recommendations, a gap the MOWI says has cast serious, legitimate doubt on the integrity of the entire public works procurement process for recent years.

All findings from the multi-agency investigation have been formally referred to the Office of the Attorney General for official legal guidance and potential follow-up enforcement action. When contacted by the Sunday Express for comment shortly before noon last Tuesday regarding his termination and the full scope of the allegations, Phillip repeatedly declined to respond, stating only: “I have no comment whatsoever.”