The Trinidad and Tobago healthcare system is implementing strategic interim solutions to address service pressures resulting from significant delays in the completion of the $1.3 billion Central Block at Port of Spain General Hospital. Health Minister Dr. Lackram Bodoe confirmed the project’s timeline has been extended to June 2026, pushing back the previously scheduled March 31 completion date.
The state-owned Urban Development Corporation of Trinidad and Tobago (UDeCOTT) reported the construction is approximately 96% complete but cited multiple complications including delayed payments, workmanship issues requiring corrective measures, and global supply chain disruptions as primary causes for the extended timeline.
Technical challenges have substantially impacted progress. Critical systems including pipeline pressurization testing revealed leaks in fire sprinkler and water systems during August-December 2025, necessitating repairs and drywall replacement. HVAC commissioning faced delays due to postponed insulation shipments from China and additional flushing requirements for chilled water lines. A significant setback occurred in January 2026 when water infiltration damaged electrical bus ducts, causing a three-day power outage that requires component replacement expected in April.
Medical gas system certification encountered obstacles when two approved American verifiers declined travel due to U.S. Embassy restrictions during Trinidad’s State of Emergency. A new certified inspector arrived in March 2026 to complete this essential verification process.
Despite these construction delays, the North-West Regional Health Authority (NWRHA) has activated multiple contingency measures to maintain healthcare standards. These include establishing an internal medicine ward at St James Medical Complex to divert eligible patients from Port of Spain General Hospital, implementing filter clinics at both facilities to separate lower-acuity cases, and enhancing emergency department staffing.
Additional improvements feature upgraded digital infrastructure through Laboratory Information and Picture Archiving systems, creation of an additional observation area in the Emergency Department, equipment procurement, and facility refurbishments. These coordinated efforts aim to optimize patient flow, strengthen emergency care capacity, and ensure continued timely medical services during the construction period.
The Ministry of Health and regional authorities emphasize their commitment to effectively managing available resources to safeguard population health while awaiting the eventual addition of 540 beds and expanded inpatient capacity upon the Central Block’s completion.