The highly anticipated reopening of the Central Block at Port of Spain General Hospital has encountered significant setbacks, pushing its completion date to June 2026 instead of the previously scheduled March 31st deadline. The Urban Development Corporation of Trinidad and Tobago (UDeCOTT) confirmed the substantial delay in the $1.3 billion, 540-bed facility project, which was originally slated to open last year.
Despite building works reaching 95.82% completion, UDeCOTT cited multiple complex challenges that have collectively contributed to the extended timeline. The corporation provided a detailed breakdown of the issues, highlighting critical infrastructure problems that emerged during the final phases of construction.
Significant pipeline pressurization issues were identified during system testing between July and December 2025. The fire sprinkler system evaluation revealed leaks throughout the piping network, necessitating extensive repairs and replacement of damaged drywall installations. Simultaneously, global supply chain disruptions caused delays in duct insulation shipments from China, affecting HVAC system commissioning between June and September 2025.
A particularly severe incident occurred on January 26, 2026, when a broken pipeline allowed water infiltration into the electrical bus duct system, causing a three-day power interruption. The damaged component requires replacement, with delivery expected in April 2026.
Additional complications arose with medical gas system certification, as two previously approved verifiers declined to travel to Trinidad and Tobago due to US Embassy travel restrictions during the State of Emergency. A new certified verifier only arrived on March 1, 2026, to begin the inspection process.
Despite these challenges, progress continues with medical equipment installation and staff training. Bed ward areas across Levels 3 to 12 reached operational readiness between December 2025 and February 2026, though specialized areas including the Pharmacy and Operating Theatre Suites remain under construction.
The project, approved by the former government in June 2017, has faced numerous obstacles including the 2018 earthquake and COVID-19 pandemic. UDeCOTT maintains its commitment to delivering the redeveloped Central Block with the highest standards of safety and functionality.
